Meeting Date:
|
|
Category:
|
|
Type:
|
|
Subject:
|
12.14 Change Orders One through Three to Bathroom Renovations at Hawthorne Avenue School and Lafayette Street School Contract 9858 |
|
|
Strategic Plans:
|
Priority 1.5 1.5 Develop a capital strategy aligned with the Long-Range Facilities Plan and strategic plan to modernize all facilities, and plan for enrollment projections, academic programs, and community needs.
|
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
WHEREAS, bids were received electronically on Tuesday, March 5, 2024 after public advertisement for Bathroom Renovations at Hawthorne Avenue School and Lafayette Street School. Request for bids were issued to thirty-two (32) vendors with four (4) vendors responding, see award analysis; and WHEREAS, the Newark Board of Education awarded a contract to Brahma Construction, 1360 Route 23, Wayne, NJ 07470 during the May 23, 2024 Board Meeting in the amount of $848,000.00. An additional twenty percent (20%) in the amount of $169,600.00 was approved for encumbrance as a contingency allowance; and WHEREAS, change order one provides for additional demolition, carpentry, masonry, toilet compartment, plumbing, Heating, Ventilation, and Air Conditioning (HVAC), electrical and accessories as a response to the City of Newark Building Department in the amount of $52,529.63; and WHEREAS, change order two provides for architectural and supervision of Mechanical, Electrical and Plumbing (MEP) work on second shift overtime rates in the amount of $103,963.00; and WHEREAS, change order three provides for MEP work to be performed during second shift overtime rates in the amount of $140,618.00; and WHEREAS, an additional one hundred twenty-seven thousand five hundred ten dollars and .63 cents ($127,510.63) is requested as an additional contingency allowance; and WHEREAS, change orders one through three were reviewed and approved by Carlos Edmundo, Acting Executive Director of Facilities Management and Krystle Whitlock, Assistant School Business Administrator. |
|
|
Funding :
|
Subject to availability of funds. 10-12-000-400-450-344-CAP-000 10-12-000-400-450-351-000-000 |
|
|
Recommendation to the Board
|
NOW THEREFORE BE IT RESOLVED that the Newark Board of Education accepts and approves the request for an additional contingency allowance in the amount of $127,510.63 and change orders one through three in the amount of $297,110.63 increasing the contract value to $1,145,110.63 and increasing the construction duration by 67 working days. EXPLANATION: To provide bathroom renovations at Hawthorne Avenue School and Lafayette Street School. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Nicole Yarbough - Purchasing Manager |
|
Signed By: |
|
Ty-Shanique Addison - Principal Fiscal Analyst |
|
Signed By: |
|
Carlos Edmundo - Acting Executive Director |
|
Signed By: |
|
Krystle Whitlock - Assistant Business Administrator |
|
Signed By: |
|
Sherelle Spriggs - Director Support Services |
|
Signed By: |
|
Valerie Wilson - School Business Administrator |
|
Signed By: |
|
Roger León - Superintendent |
|
|
|
|
|
|
|