|
|
|
|
|
|
Meeting Date:
|
9/28/2023 - 6:00 PM
|
Category:
|
Purchasing
|
Type:
|
Action
|
Subject:
|
11.26 Change Orders One through Three to Façade Repairs and Roof Replacement at West Side High School Contract 9466R
|
Strategic Plans:
|
Priority 1.5 1.5 Develop a capital strategy aligned with the Long-Range Facilities Plan and strategic plan to modernize all facilities, and plan for enrollment projections, academic programs, and community needs.
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
WHEREAS, the Newark Board of Education originally advertised to receive bids on Wednesday, March 30, 2022 for Façade Repairs and Roof Replacement at West Side High School, request for bids were issued to twenty (20) vendors with zero vendors responding; and WHEREAS, the Newark Board of Education re-advertised to receive bids on Tuesday, April 26, 2022 for Façade Repairs and Roof Replacement at West Side High School, bids were issued to twenty-three (23) vendors with seven (7) vendors responding; and WHEREAS, the Newark Board of Education awarded a contract to Punjab Restoration Co., LLC., 39 E. Asbury Anderson Rd., Washington, NJ 07882 for Façade Repairs and Roof Replacement at West Side High School during the May 26, 2022 Board Meeting in the amount of $3,606,000.00. An additional twenty percent (20%) in the amount of $721,200.00 was approved for encumbrance as a contingency allowance; and WHEREAS, change order one provides for temporary removal of three (3) T-Mobile antennas and associated cable trays to accommodate new roof installation and reinstallation once work is complete in the amount of $33,330.00; and WHEREAS, change order two provides for temporary removal of three (3) Verizon antennas and associated cable trays to accommodate new roof installation and reinstallation once work is complete in the amount of $96,250.00; and WHEREAS, change order three provides for disassembly and rebuilding of displaced parapet section including reroofing and flashing in the amount of $37,500.00; and WHEREAS, change orders one through three were reviewed and approved by Carlos Edmundo, Acting Executive Director of Facilities Management and Krystle Whitlock, Assistant School Business Administrator.
|
Funding :
|
Subject to availability of funds. 20-20-492-400-450-351-034-000 30-30-000-401-450-351-190-000
|
Recommendation to the Board:
|
NOW THEREFORE BE IT RESOLVED that the Newark Board of Education accepts and approves change orders one through three in the amount of $167,080.00 increasing the contract value to $3,773,080.00. Remaining contingency will be $554,120.00. EXPLANATION: Additional work required to complete the façade repairs and roof replacement project at West Side High School.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Nicole Yarbough - Purchasing Manager
|
|
Signed By:
|
|
Ty-Shanique Addison - Principal Fiscal Analyst
|
|
Signed By:
|
|
Carlos Edmundo - Acting Executive Director
|
|
Signed By:
|
|
Krystle Whitlock - Assistant Business Administrator
|
|
Signed By:
|
|
Sherelle Spriggs - Senior Purchasing Manager
|
|
Signed By:
|
|
Valerie Wilson - School Business Administrator
|
|
Signed By:
|
|
Roger León - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Daniel Gonzalez Moved, Member Josephine Garcia seconded to approve the Original motion 'NOW THEREFORE BE IT RESOLVED that the Newark Board of Education accepts and approves change orders one through three in the amount of $167,080.00 increasing the contract value to $3,773,080.00. Remaining contingency will be $554,120.00. EXPLANATION: Additional work required to complete the façade repairs and roof replacement project at West Side High School.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0. | The motion Carried 7 - 0 | | | Allison K. James-Frison | Yes | Crystal Williams | Yes | Daniel Gonzalez | Yes | Hasani Council | Yes | A'Dorian Murray-Thomas | Yes | Josephine Garcia | Yes | Dawn Haynes | Yes | |
|
|
|
|
|
|